A business analyst has just completed an elicitation event. What stakeholder(s) is/are involved in the documentation of the elicitation results?
A.
Business analyst and key stakeholders
B.
Business analyst
C.
Project manager, project team, and business analyst
D.
Project manager, business analyst, and project sponsor