The initial high-level listing of requirements in a change-driven approach is also known as what?

A.
Requirements envisioning
Answers
A.
Requirements envisioning
B.
Requirements foundation
Answers
B.
Requirements foundation
C.
Product scope
Answers
C.
Product scope
D.
Project scope
Answers
D.
Project scope
Suggested answer: A

Explanation:

The initial high-level listing of requirements in a change-driven approach is also known as requirements envisioning.

Answer D is incorrect. The project scope defines all of the required work to satisfy the requirements of the project.

Answer C is incorrect. The product scope defines all of the features and functions of the thing, solution, or service the project or organization will create.

Answer B is incorrect. Requirements foundation is not a valid term for business analysis.