You are the business analyst for your organization and your requirements for the endeavor have recently been approved. Your organization creates a baseline for the requirements based on the approval of the requirements. What must happen in your business analysis activities if the requirements for your endeavor need to be changed?

A.
You'll need to create new baselines.
Answers
A.
You'll need to create new baselines.
B.
You'll need to implement configuration management.
Answers
B.
You'll need to implement configuration management.
C.
You'll need to use a change control system.
Answers
C.
You'll need to use a change control system.
D.
You'll need to create requirements versioning.
Answers
D.
You'll need to create requirements versioning.
Suggested answer: C

Explanation:

If an organization baselines requirements and the requirements change after approval, then the organization must use a change control system. The change control system helps to manage desired changes, provides governance for the change, and documents the proposed change.

Answer A is incorrect. Rebaselining is rarely appropriate; sending the changes through the change control system is the best answer.

Answer D is incorrect. Requirements versioning may be appropriate if the changes are actually approved after they've passed through the change control system.

Answer B is incorrect. Configuration management controls the features and functions of the requirements. The best choice is to send the proposed change through the change control system.