Which stakeholder map shows the relative influence, impact, and relation of stakeholders by plotting them closer to or farther away from the solution?

A.
RACI Matrix
Answers
A.
RACI Matrix
B.
Onion diagram
Answers
B.
Onion diagram
C.
Control chart
Answers
C.
Control chart
D.
Tornado diagram
Answers
D.
Tornado diagram
Suggested answer: B

Explanation:

An onion diagram shows the relative influence, impact, and relation of stakeholders by plotting them closer to or farther away from the solution. It is called an onion diagram because plotting of the stakeholders is done in ovals which, when completed, looks like an onion sliced in half.

Answer D is incorrect. A tornado diagram is often used to show opposing forces for a solution or issue. Answer A is incorrect. The RACI matrix explains the roles of the people involved in business analysis activities. It depicts stakeholders as having one or more of the following responsibilities for a given task or deliverable:

[R]. Responsible does the work [A]. Accountable is the decision maker (only one) [C]. Consulted must be consulted prior to the work and gives input. [I]. Informed means that they must be notified of the outcome

Answer C is incorrect. A control chart is a quality control tool that shows the results of measurements over time.