Why is it important to have a requirements signoff process for approved requirements?

A.
It formalizes the agreement by the stakeholders that the requirements are complete and accurate.
Answers
A.
It formalizes the agreement by the stakeholders that the requirements are complete and accurate.
B.
It confirms that the project sponsor and the project manager are in agreement with the business analyst about the accuracy and completeness of the requirements.
Answers
B.
It confirms that the project sponsor and the project manager are in agreement with the business analyst about the accuracy and completeness of the requirements.
C.
It holds stakeholders accountable for the cost and schedule of the requirements.
Answers
C.
It holds stakeholders accountable for the cost and schedule of the requirements.
D.
It allows the project manager to begin the project.
Answers
D.
It allows the project manager to begin the project.
Suggested answer: A

Explanation:

Signoff formalizes the agreement and confirmation that the requirements are accurate and complete. Answer C is incorrect. This isn't a valid statement, as signoff shows the agreement of the stakeholders that the requirements are complete.

Answer D is incorrect. This isn't a valid statement.

Answer B is incorrect. This isn't a valid statement, as the agreement is among the stakeholders, not between the project manager and the project sponsor.