List of questions
Related questions
Question 182 - CCBA discussion
Project Communication Management includes the processes required to .
A.
Ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information.
B.
Identify, define, combine, unify, and coordinate the various processes and project management activities with the Project Management Process Groups.
C.
Manage timely completion of the project.
D.
Organize, manage, and lead the project team.
Your answer:
0 comments
Sorted by
Leave a comment first