Question 189 - CCBA discussion

Report
Export

The RGQ Organization utilizes a change log. What is a change log?

A.
It is a document that tracks all unauthorized changes to the project solution.
Answers
A.
It is a document that tracks all unauthorized changes to the project solution.
B.
It is a document that records all change requests for the project.
Answers
B.
It is a document that records all change requests for the project.
C.
It is a document that tracks the changes that have been received, including their implementation to the project solution.
Answers
C.
It is a document that tracks the changes that have been received, including their implementation to the project solution.
D.
It is a document that tracks all characteristics and status of changes that have been received.
Answers
D.
It is a document that tracks all characteristics and status of changes that have been received.
Suggested answer: D

Explanation:

A change log tracks all characteristics of a proposed change request and it status. Answer A is incorrect. The change log tracks change requests and its status.

Answer B is incorrect. This description is close to being accurate, but the change log records the status of the change request too.

Answer C is incorrect. This statement is false because a request for change can be made, but it does not necessarily mean that the change will be implemented into the project.