Before requirements can actually be approved to be managed, what must be true about the requirements?

A.
Requirements must support the solution scope.
Answers
A.
Requirements must support the solution scope.
B.
Requirements must be approved by the technical review board.
Answers
B.
Requirements must be approved by the technical review board.
C.
Requirements must support the requirements management plan.
Answers
C.
Requirements must support the requirements management plan.
D.
Requirements are governed by the requirements management plan.
Answers
D.
Requirements are governed by the requirements management plan.
Suggested answer: A

Explanation:

For requirements to be approved, they must support the solution scope. The solution scope defines what's in and out of the range of requirements for business analysis activities.

Answer B is incorrect. A technical review doesn't approve requirements; the solution scope defines what's approved based on what's in alignment with the scope.

Answer C is incorrect. The requirements management plan doesn't affect the requirements that are or are not approved.

Answer D is incorrect. While this statement may be somewhat true, it doesn't define how requirements are approved before their governance.