What term is given to the collection of notes and diagrams used by the business analyst to develop the requirements during the requirements development process?

A.
Work product
Answers
A.
Work product
B.
Deliverable
Answers
B.
Deliverable
C.
Supporting requirements package detail
Answers
C.
Supporting requirements package detail
D.
Work package
Answers
D.
Work package
Suggested answer: A

Explanation:

Work product is the business analyst term for the collection of notes and diagrams used by the business analyst to develop the requirements.

Answer D is incorrect. A work package is the smallest item in the work breakdown structure.

Answer B is incorrect. Deliverable is a specific output of the business analysis process that the business analyst has agreed to produce.

Answer C is incorrect. This is not a valid business analysis term.