You are creating the solution scope for an identified problem in your organization. You are working with several stakeholders during this process including the domain subject matter expert, the implementation subject matter expert, the project manager, and the sponsor. Which of these stakeholders will be responsible for writing the project scope?

A.
Business analyst
Answers
A.
Business analyst
B.
Project manager
Answers
B.
Project manager
C.
Domain subject matter expert
Answers
C.
Domain subject matter expert
D.
Sponsor
Answers
D.
Sponsor
Suggested answer: B

Explanation:

The project manager is responsible for writing the project scope. The solution scope serves as an input the project charter, which is needed for the project scope.

Answer A is incorrect. The business analyst does not write the project scope.

Answer D is incorrect. The sponsor doesn't write the project scope but she may approve the project scope. Answer C is incorrect. The domain subject matter expert helps to identify the affected organizational units, lines of business, and prioritization of the required capabilities defined in the solution scope.