You are hired as a contract project manager for Dreams Unlimited Inc. The project involves setting up ten servers and fifty client computers on the network. From past experience, you know it takes around fifteen hours to install, test, and finalize a server, while it takes only ten hours for a client. You consider these data for making an estimate of schedule of the task. Which of the following estimation techniques has been used?
A.
Bottom-up
B.
Schedule performance index
C.
Parametric modeling
D.
Analogous