Which basis for prioritization allows the project team to work initially with lower-risk requirements first?

A.
Quantitative ranking
Answers
A.
Quantitative ranking
B.
Positive risk ranking
Answers
B.
Positive risk ranking
C.
Relationship to other requirements
Answers
C.
Relationship to other requirements
D.
Implementation difficulty
Answers
D.
Implementation difficulty
Suggested answer: D

Explanation:

This approach prioritizes requirements that are easiest to implement first. This allows the project team to work with the lowest risk requirements first to gain familiarity with the requirements. This is especially useful with a new technology or materials where a learning curve is involved.

Answer A is incorrect. There is not a prioritization basis for quantitative ranking. Answer B is incorrect. There is not a prioritization basis called positive risk ranking.

Answer C is incorrect. The basis of relationship to other requirements is useful for requirements that need to be implemented so that other requirements, which are dependent on the initial requirements, can be implemented.