You are the business analyst for your organization and are working on organizing the identified requirements for a new solution. Nancy, your assistant in this process, says that these requirements aren't very complex. You agree but add that it's this thing that makes the overall solution complex.

What thing adds to the level of complexity among requirements?

A.
Relationships among the requirements
Answers
A.
Relationships among the requirements
B.
Management in the project
Answers
B.
Management in the project
C.
Cost and schedule constraints
Answers
C.
Cost and schedule constraints
D.
Stakeholders in the project
Answers
D.
Stakeholders in the project
Suggested answer: A

Explanation:

The relationships and inter-dependencies among the requirements add to the complexity of the requirements. Answer D is incorrect. Stakeholder management can be cumbersome, but the question was asking for a requirements characteristic, so this choice is incorrect.

Answer B is incorrect. Management in the project can add to the project complexity, but realistically management should stay out of the business analyst's duties. In addition, the question was asking about the complexity among the requirements.

Answer C is incorrect. Cost and schedule constraints deal more with the project implementation than with the identified requirements.