If an organization wants to re-use requirements, where should the defined requirements be kept?

A.
Requirements management plan
Answers
A.
Requirements management plan
B.
Requirements repository
Answers
B.
Requirements repository
C.
Solution scope
Answers
C.
Solution scope
D.
Project management plan
Answers
D.
Project management plan
Suggested answer: B

Explanation:

Requirements that are re-used in an organization are ideally kept in a requirements repository. One person should be identified to manage and control the repository.

Answer A is incorrect. Requirements for the current endeavor are kept in the requirements management plan, but not the set of requirements that will be reused.

Answer D is incorrect. The project management plan is not a valid answer, as this plan defines how the project will be planned, executed, monitored and controlled, and closed.

Answer C is incorrect. The solution scope is not a place where requirements that are reused will be kept and maintained.