Question 273 - CCBA discussion

Report
Export

You are the business analyst for your organization and you're working with several stakeholders to identify, manage, and approve requirements. Your organization requires using a plan-driven approach to business analysis and changing management. In this approach, who is most likely to approve changes to requirements?

A.
Change control board
Answers
A.
Change control board
B.
Requirements owner
Answers
B.
Requirements owner
C.
Project sponsor
Answers
C.
Project sponsor
D.
Project manager
Answers
D.
Project manager
Suggested answer: A

Explanation:

Change Control Board is a collection of managers, requirement owners, and key stakeholders that review the validity, need, impact, and full consideration of a change request to determine whether the change should be approved or declined. This approach is the most likely answer for a plan-driven business analysis environment.

Answer B is incorrect. The requirements owner isn't the best answer for a plan-driven approach.

Answer C is incorrect. The project sponsor won't make this decision.

Answer D is incorrect. The project manager rarely has change control authority over requirements, so this choice is not valid.