Question 323 - CCBA discussion
A business analyst (BA) was asked to send the requirement details to the project manager (PM), director, vice president (VP), and Chief Information Officer (CIO). The BA shares the complete set of requirements to the PM and director, while creating a summarized version for the VP and CIO. Which aspect of requirement specification and modeling was the BA performing?
A.
Perform stakeholder analysis
B.
Organize requirements categories
C.
Determine approval authority
D.
Implement appropriate level of abstraction