A business analyst (BA) is planning the requirements attributes. The BA received a long list of requirements that must be implemented in different phases. Which requirements attribute can the BA include to allocate the requirements to the proper phase?

A.
Status
Answers
A.
Status
B.
Author
Answers
B.
Author
C.
Priority
Answers
C.
Priority
D.
Source
Answers
D.
Source
Suggested answer: C

Explanation:

Priority: indicates relative importance of requirements. Priority can refer to the relative value of a requirement or to the sequence in which it will be implemented.