Question 376 - CCBA discussion
A business analyst (BA) is planning the traceability approach for a project. Why should the BA conduct this planning activity?
A.
To verify that project information is represented at a high level of abstraction
B.
To document the relationship between the different phases of the project for different stakeholders
C.
To ensure the approach provides enough detail to add value without excessive overhead
D.
To associate information with individual or related groups of requirements