A business analyst (BA) is planning the traceability approach for a project. Why should the BA conduct this planning activity?

A.
To verify that project information is represented at a high level of abstraction
Answers
A.
To verify that project information is represented at a high level of abstraction
B.
To document the relationship between the different phases of the project for different stakeholders
Answers
B.
To document the relationship between the different phases of the project for different stakeholders
C.
To ensure the approach provides enough detail to add value without excessive overhead
Answers
C.
To ensure the approach provides enough detail to add value without excessive overhead
D.
To associate information with individual or related groups of requirements
Answers
D.
To associate information with individual or related groups of requirements
Suggested answer: D

Explanation:

The traceability approach is based on: the complexity of the domain, the number of views of requirements that will be produced, any requirement-related risks, organizational standards, applicable regulatory requirements, and an understanding of the costs and benefits involved with tracing.

Business analysts plan to ensure the approach is at a level of detail to add value without excessive overhead.