A business analyst (BA) has completed documenting requirements and to save time, recommends sharing the requirements document with the development team to fast-track development immediately. What issue may arise by doing so?

A.
Stakeholders may refuse the solution.
Answers
A.
Stakeholders may refuse the solution.
B.
Requirements metrics may not be measurable.
Answers
B.
Requirements metrics may not be measurable.
C.
The BA may significantly impact other aspects of the project timeline.
Answers
C.
The BA may significantly impact other aspects of the project timeline.
D.
The business need may change.
Answers
D.
The business need may change.
Suggested answer: B