Question 391 - CCBA discussion
A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal. Which of the following would the BA classify as a project risk?
A.
Customer service ratings will increase with the new system
B.
Current infrastructure may not support increased performance
C.
Expenditures are currently below budgeted estimates
D.
Support calls will increase if the change is not performed