A change is desired in a project after the requirements are signed off and after technical design has started. The stakeholders want an additional product to be developed as part of the project. What tool can be used by the business analyst (BA) to assess the impact of the change?

A.
Concept modelling
Answers
A.
Concept modelling
B.
Requirements architecture
Answers
B.
Requirements architecture
C.
Backlog management
Answers
C.
Backlog management
D.
Balanced scorecard
Answers
D.
Balanced scorecard
Suggested answer: B