During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project's scope. The business analyst (BA) facilitating the workshop should:

A.
note the issue in the Issue Register to be considered by the Project Manager.
Answers
A.
note the issue in the Issue Register to be considered by the Project Manager.
B.
ignore the stakeholder's comment and proceed with the agenda.
Answers
B.
ignore the stakeholder's comment and proceed with the agenda.
C.
consider the issue's impact on the project and gain agreement with stakeholders on the next step.
Answers
C.
consider the issue's impact on the project and gain agreement with stakeholders on the next step.
D.
request the stakeholder to explain the issue further so that possible solutions can be discussed.
Answers
D.
request the stakeholder to explain the issue further so that possible solutions can be discussed.
Suggested answer: C