Question 499 - CCBA discussion
A stakeholder has requested an extremely detailed resolution to an issue during current state analysis that may consume about 20% of the estimated project effort. How should the business analyst (BA) handle the situation?
A.
Ask the project sponsor for additional funding
B.
Escalate the request to the project manager for reevaluation of the plan
C.
Spend the required effort to develop the detail
D.
Explain that the degree of effort may not be necessary at this stage