Which of the following is the BEST outcome measure to determine the effectiveness of IT nsk management processes?

A.
Frequency of updates to the IT risk register
Answers
A.
Frequency of updates to the IT risk register
B.
Time lag between when IT risk is identified and the enterprise's response
Answers
B.
Time lag between when IT risk is identified and the enterprise's response
C.
Number of events impacting business processes due to delays in responding to risks
Answers
C.
Number of events impacting business processes due to delays in responding to risks
D.
Percentage of business users satisfied with the quality of risk training
Answers
D.
Percentage of business users satisfied with the quality of risk training
Suggested answer: C