List of questions
Related questions
Question 27 - COBIT Design and Implementation discussion
Which of the following describes the difference between the Risk Profile design factor and the I&T-Related Issues design factor?
A.
IT risk scenarios describe potential events that could impact the organization in the future, whereas IT issues describe events or current situations affecting the organization.
B.
IT risk scenarios are more detailed and IT issues are more summarized and the organization can decide which one to use when designing its governance system
C.
IT issues describe potential events that could impact the organization in the future, whereas IT risk scenarios describe events or current situations affecting the organization.
D.
IT risk scenarios have been described in more detail the COBIT 2019 Design Guide that IT issues in order to cover a wide range of potential risk
Your answer:
0 comments
Sorted by
Leave a comment first