In a project that is feature-rich but time-poor, which is the most reasonable approach to risk analysis?

A.
Conduct a full risk analysis, including weighted likelihood and impact ratings for each item
Answers
A.
Conduct a full risk analysis, including weighted likelihood and impact ratings for each item
B.
Use a lightweight approach and assign relative importance of each identified item
Answers
B.
Use a lightweight approach and assign relative importance of each identified item
C.
Skip the risk analysis step and proceed to test execution based on experience
Answers
C.
Skip the risk analysis step and proceed to test execution based on experience
D.
Concentrate on the functional capabilities and disregard the physical capabilities of the device since those should be tested by the manufacturer
Answers
D.
Concentrate on the functional capabilities and disregard the physical capabilities of the device since those should be tested by the manufacturer
Suggested answer: B

Explanation:

B is correct since this is a time challenged project. If there were adequate time, A might be the right answer, depending on the criticality of the product. C is never a good idea since even minimal risk analysis is needed to focus the testing. D is risky because the interaction of the application with the physical capabilities of the device still need to be tested.