Question 30 - DASM discussion
A team has completed the work in their Aeration backlog earlier than expected. There is still three days left of the iteration, what should the team do now?
A.
Work on non-critical tasks until the product owner can assign them more work.
B.
Work with the product owner to pull more work from the product backlog into their iteration backlog.
C.
Report the differences in completion time so the next iteration can be planned more efficiently.
D.
Wait for the other groups to complete their work prior to doing anything else.