How should iterations for an agile project be planned?

A.
At the retrospective meetings to ensure nothing is missed from one iteration to the next.
Answers
A.
At the retrospective meetings to ensure nothing is missed from one iteration to the next.
B.
Throughout the project by using iteration reviews to continuously improve quality.
Answers
B.
Throughout the project by using iteration reviews to continuously improve quality.
C.
At the beginning of each iteration by puling from the product backlog.
Answers
C.
At the beginning of each iteration by puling from the product backlog.
D.
Iteratively by the product owner to ensure global optimization.
Answers
D.
Iteratively by the product owner to ensure global optimization.
Suggested answer: C

Explanation:

In Agile and Disciplined Agile practices, iterations are planned at the beginning of each iteration during an iteration planning meeting. The team, along with the product owner, pulls the highest-priority items from the product backlog that they believe can be completed within the iteration. This ensures that the work is well-defined, understood, and aligned with the current goals and priorities.

A . Retrospective meetings focus on reflecting on the past iteration to identify improvements, not planning the next iteration.

B . Using iteration reviews improves quality but is not about planning.

D . Iteratively planning by the product owner alone does not ensure team alignment or collaboration, which is essential in Agile.

Therefore, the correct answer is C. At the beginning of each iteration by pulling from the product backlog.