Your team wants to work in an Agile manner and has been asked to provide a cost estimate for the project even though management recognizes that the requirements will evolve overtime. Which process goal is most likely to offer potential techniques to address this?

A.
Project Management
Answers
A.
Project Management
B.
Plan the Release
Answers
B.
Plan the Release
C.
Explore Scope
Answers
C.
Explore Scope
D.
Address Changing Stakeholder Needs
Answers
D.
Address Changing Stakeholder Needs
Suggested answer: C