Question 188 - DASSM discussion
For an Agile or Lean project team, which best describes the aim of the Inception phase?
A.
The team develops a plan to build a minimum business increment (MBI) that meets the needs of their stakeholders
B.
The team performs sufficient work to develop a plan for performing initial requirements modeling, architecture modeling, risk assessment and business case development
C.
The team develops a plan to build a consumable solution that meets the needs of their stakeholders
D.
The team performs sufficient work to initiate the endeavor and obtain agreement as to the overall vision with their stakeholders
Your answer: