Universal Containers (UC) wants to implement Service Cloud using Agile methodology. How should the consultant recommend delivering a successful implementation?

A.
set a cutoff date of 1.5 months before user acceptance testing for any change requests.
Answers
A.
set a cutoff date of 1.5 months before user acceptance testing for any change requests.
B.
Generate continuous feedback from the project team, and adjust the requirements and deliverables accordingly.
Answers
B.
Generate continuous feedback from the project team, and adjust the requirements and deliverables accordingly.
C.
Deliver the entire project simultaneously so as to present UC with a completed solution.
Answers
C.
Deliver the entire project simultaneously so as to present UC with a completed solution.
D.
Schedule a meeting with the UC executives at the start of the project to generate all the requirements.
Answers
D.
Schedule a meeting with the UC executives at the start of the project to generate all the requirements.
Suggested answer: B

Explanation:

Generating continuous feedback from the project team, and adjusting the requirements and deliverables accordingly is a key principle of Agile methodology. It allows for iterative and incremental development, which can lead to a successful implementation of Service Cloud. Verified

Reference: : https://trailhead.salesforce.com/en/content/learn/modules/agile-basics/agile-basics-principles : https://trailhead.salesforce.com/en/content/learn/modules/agile-basics/agile-basics-methodologies