Question 231 - Certified Service Cloud Consultant discussion
A consultant is working on a Service Cloud implementation with a fixed budget and timeline. Additional requirements were discovered early on that will result in the project exceeding timeline and budget constraints.
What is the first step the consultant should take to address the issue?
A.
Prepare a change order to account for the additional requirements and communicate the new project schedule,
B.
Incorporate the additional requirements to the project scope and continue with the original project schedule.
C.
Document the gap in requirements and discuss the schedule and budget impact with the project team.