Who is responsible for the sizing / estimate of the product backlog?

A.
Scrum team
Answers
A.
Scrum team
B.
The product owner
Answers
B.
The product owner
C.
Developers
Answers
C.
Developers
D.
The scrum master lets them know whether they need to be preset
Answers
D.
The scrum master lets them know whether they need to be preset
Suggested answer: C

Explanation:

The scrum guide says: 'The Developers who will be doing the work are responsible for the sizing. The Product Owner may influence the Developers by helping them understand and select trade-offs.'