How much time must a product owner spend with the developers?

A.
However much time the developers ask the PO to be present
Answers
A.
However much time the developers ask the PO to be present
B.
40%, or more depending on stakeholders
Answers
B.
40%, or more depending on stakeholders
C.
100%
Answers
C.
100%
D.
Enough to be aware of the increment's value at the sprint review
Answers
D.
Enough to be aware of the increment's value at the sprint review
Suggested answer: A

Explanation:

This should not be too much in a healthy situation, and this also doesn't imply that the developers can control the PO. But when the developers need the product owner to clarify or renegotiate the work to be done, it will be an impediment if the PO is not available.