Question 15 - PSD discussion

Report
Export

A scrum master is working with developers that are spread over different locations. They have a variety of meeting rooms and the daily scrum is a logistic struggle every day. What actions should the scrum master take?

A.
Allow the developers to self-manage and decide what to do their selves.
Answers
A.
Allow the developers to self-manage and decide what to do their selves.
B.
Raise it as an impediment and make sure that management solves it.
Answers
B.
Raise it as an impediment and make sure that management solves it.
C.
Create a schedule and alternate who is responsible for the daily scrum logistics
Answers
C.
Create a schedule and alternate who is responsible for the daily scrum logistics
D.
Decide the best solution and arrange a meeting to inform the developers.
Answers
D.
Decide the best solution and arrange a meeting to inform the developers.
Suggested answer: A

Explanation:

Self management is important. All the other options the scrum master takes a decision by himself, it is better if the solution comes from the development team.