Question 59 - PSD discussion
When do the developers participate in the product backlog refinement?
A.
Never, it is the sole responsibility of the Product owner to refine the backlog
B.
Only during the sprint planning
C.
Anytime during the sprint
D.
Only during the refinement meetings planned by the PO
Your answer:
0 comments
Sorted by
Leave a comment first