Question 86 - PSD discussion

Report
Export

How much time does Product backlog refinement take?

A.
25% of the sprint capacity
Answers
A.
25% of the sprint capacity
B.
As much as needed without endangering the Sprint goal
Answers
B.
As much as needed without endangering the Sprint goal
C.
10% of the senior developers
Answers
C.
10% of the senior developers
Suggested answer: B

Explanation:

The refinement is very important and can take quite some time for that reason, however, it should not endanger the sprint goal.