Which three of the following are feedback loops in scrum?

A.
Release planning
Answers
A.
Release planning
B.
Daily scrum
Answers
B.
Daily scrum
C.
Sprint review
Answers
C.
Sprint review
D.
Sprint retrospective
Answers
D.
Sprint retrospective
E.
Refinement meeting
Answers
E.
Refinement meeting
Suggested answer: B, C, D

Explanation:

Refinement meeting and release planing are no scrum events. The others are, and they are all about feedback: inspection and adaptation. (And in order for the inspection to have a good outcome, the artifacts need to be transparent)