How is the management external to the Scrum team involved in the daily scrum?

A.
The product owner speaks on their behalf
Answers
A.
The product owner speaks on their behalf
B.
The developers self-manage and they are the only management required at the daily scrum
Answers
B.
The developers self-manage and they are the only management required at the daily scrum
C.
The scrum master speaks on their behalf
Answers
C.
The scrum master speaks on their behalf
D.
The scrum master lets them know whether they need to be preset
Answers
D.
The scrum master lets them know whether they need to be preset
Suggested answer: B

Explanation:

Only the developers need to be present at the daily scrum, since they are self managing, that's all the management necessary.