Question 144 - PSPO-I discussion
Which of the following are criteria to order Product Backlog items?
(choose the best three answers)
A.
The value of the Product Backlog items.
B.
The availability of the Scrum Master.
C.
Dependencies between Product Backlog items.
D.
Their relevance to achieving the Product Goal.
E.
The number of stakeholders who approve of the item.
Your answer: