Question 145 - PSPO-I discussion

Report
Export

When does a Developer become accountable for an item in the Sprint Backlog?

(choose the best answer)

A.
During the Daily Scrum.
Answers
A.
During the Daily Scrum.
B.
As soon as a Developer on the Scrum Team can accommodate more work.
Answers
B.
As soon as a Developer on the Scrum Team can accommodate more work.
C.
Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.
Answers
C.
Never. All Developers on the Scrum Team share accountability for items in the Sprint Backlog.
D.
At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.
Answers
D.
At Sprint Planning when all of the Sprint Backlog items are split evenly across the Developers.
Suggested answer: C

Explanation:

The Developers on the Scrum Team share accountability for the Sprint Backlog, which is a forecast of the work and the plan to deliver the Sprint Goal12.The Sprint Backlog is dynamic and can be updated by the Developers as more is learned during the Sprint34.The Developers are not individually accountable for the items in the Sprint Backlog, nor are they assigned by the Scrum Master or the Product Owner5.