What is the accountability of the Product Owner during Sprint 0?

(choose the best answer)

A.
Determine the composition of the Scrum Team to meet the release plan.
Answers
A.
Determine the composition of the Scrum Team to meet the release plan.
B.
There is no such thing as Sprint 0.
Answers
B.
There is no such thing as Sprint 0.
C.
Create the overall release plan to ensure that organizational goals are met.
Answers
C.
Create the overall release plan to ensure that organizational goals are met.
D.
Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
Answers
D.
Make sure enough Product Backlog items are refined to fill the first 3 Sprints.
E.
Gathering, eliciting, and analyzing the requirements to build the Product Backlog.
Answers
E.
Gathering, eliciting, and analyzing the requirements to build the Product Backlog.
Suggested answer: B

Explanation:

Sprint 0 is a term that some organizations use to describe a phase of work before the first official Sprint, where they do some upfront planning, design, architecture, or analysis1.However, this term is not consistent with the Scrum framework, which does not prescribe any pre-Sprint activities or phases2. Scrum starts with a Product Backlog that contains at least one valuable and feasible Product Goal, and enough Product Backlog items to initiate the first Sprint[3][3].The Product Owner is accountable for maximizing the value of the product and the work of the Developers, and for managing the Product Backlog4. The Product Owner does not have any specific accountability during Sprint 0, because Sprint 0 is not a part of Scrum.

1:Sprint Zero: A Good Idea or Not?, Scrum Alliance, accessed on December 16, 2023

2:The Scrum Guide, November 2020, p. 5

[3][3]:The Scrum Guide, November 2020, p. 9

4:The Scrum Guide, November 2020, p. 6

asked 23/09/2024
Ronald Armas
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first