Question 160 - PSPO-I discussion
Who determines how many Product Backlog items the Developers select for a Sprint?
(choose the best answer)
A.
The Scrum Team
B.
The Developers.
C.
The Product Owner.
D.
The Scrum Master.
E.
The stakeholders attending Sprint Planning.