True or False: A Nexus Integration Team is accountable for ensuring that a Integrated

Increment is produced at least once a Sprint.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: B

Explanation:

A Nexus Integration Team is not accountable for ensuring that an Integrated Increment is produced at least once a Sprint. The Nexus Integration Team is a specialized Scrum Team that provides services and guidance to the Scrum Teams in the Nexus to ensure that the Integrated Increment is produced every Sprint 11. However, the Nexus Integration Team is not accountable for the integration of the work of the individual Scrum Teams, as this is the responsibility of the Scrum Teams themselves 22. The Nexus Integration Team helps the Scrum Teams to coordinate, coach, and supervise the application of Nexus and the operation of Scrum, but it does not take over their work or accountability 33. Therefore, the statement is false.

asked 23/09/2024
MOHAMED RIAZ MOHAMED IBRAHIM
40 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first