Question 37 - SPS discussion
Which statements are true regarding using Scrum for large-scale product delivery?
(choose the best two answers)
A.
Splitting a team member's time between multiple Scrum Teams is often less productive than focusing that team member on a single team's Sprint Backlog.
B.
Scrum requires all team members work full time on a single team.
C.
Changes to the core Scrum framework are needed to be successful with Scrum at large-scale.
D.
A well-structured and refined Product Backlog can minimize and often eliminate dependencies between multiple Scrum Teams working together on a product during a Sprint.