True or False: Using Scrum ensures that adding more resources to a product delivery effort proportionally increases the value delivered.

A.
True
Answers
A.
True
B.
False
Answers
B.
False
Suggested answer: B

Explanation:

Using Scrum does not ensure that adding more resources to a product delivery effort proportionally increases the value delivered. In fact, adding more resources may have the opposite effect, as it can introduce more complexity, communication overhead, coordination challenges, and integration issues that can reduce the productivity and quality of the Scrum Teams 12. Scrum does not prescribe a specific team size or composition, but it does recommend that the Scrum Team is small enough to remain nimble and large enough to complete significant work within a Sprint 3. Scrum also emphasizes the importance of delivering a potentially releasable increment of the product at least once per Sprint, which enables the Scrum Team and the stakeholders to inspect the value delivered and adapt accordingly 4. Therefore, using Scrum does not guarantee that adding more resources will increase the value delivered, but rather that delivering value frequently and incrementally will optimize the value delivery.

asked 23/09/2024