If two Scrum Teams are added to a product that previously had only one Scrum Team, what will be the immediate impact on the productivity of the original Scrum Team?

(choose the best answer)

A.
Its productivity is likely to stay the same.
Answers
A.
Its productivity is likely to stay the same.
B.
Its productivity is likely to decrease.
Answers
B.
Its productivity is likely to decrease.
C.
Its productivity is likely to increase.
Answers
C.
Its productivity is likely to increase.
Suggested answer: B