You have been assigned as the Scrum Master of six new Scrum Teams that will build one product. What conditions should you strive for in this scenario?
(choose the best two answers)
A.
There should be six Product Owners, one for each Scrum Team.
B.
There should be six Product Owners, one of whom is chief Product Owner.
C.
The product has one Product Backlog.
D.
There should be only one Product Owner who is accountable for the success of the product.
E.
Each Scrum Team should have a separate Product Backlog.
Your answer: