From the list below, what is the most important concern for multiple Scrum Teams when they are working from the same Product Backlog?
(choose the best answer)
A.
Meeting original scope projections.
B.
Minimizing dependencies between teams.
C.
Clear definition of requirements.
D.
Making sure there is enough work for everyone on every team.