Question 1 - CIS-SPM discussion

Report
Export

The color band at the top of the project card in Project Workspace displays what project attribute?

A.
Status
Answers
A.
Status
B.
Risk
Answers
B.
Risk
C.
State
Answers
C.
State
D.
Issues
Answers
D.
Issues
Suggested answer: A

Explanation:

According to the ServiceNow documentation1, the color band at the top of the project card in Project Workspace displays the project status. The project status is a calculated field that indicates the health of the project based on the schedule, cost, and scope variance. The color band can be green, yellow, or red, depending on the status value. The other options are incorrect because:

B) Risk: The risk is a potential problem that could affect the project or its outcome.The risk level is displayed as a circle icon on the project card, not as a color band2.

C) State: The state is the current phase of the project, such as Draft, Planning, Work in Progress, or Closed.The state is displayed as a text field on the project card, not as a color band3.

D) Issues: The issues are the actual problems that affect the project or its outcome.The number of issues is displayed as a badge icon on the project card, not as a color band4.

1: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/concept/c_ProjectWorkspace.html2: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/task/t_CreateARisk.html3: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/reference/r_ProjectTable.html4: https://docs.servicenow.com/bundle/vancouver-it-business-management/page/product/project-management/task/t_CreateAnIssue.html